According to the plan, in the first quarter of 2017, the Cat Linh – Ha Dong urban railway project will complete the construction and installation of architectural decoration including depots and structures in the depot area and put into operation. from 10/2017.
Le Kim Thanh – Director of the railway project management board, Ministry of Transport said that from March to July 2017, the unit will install equipment items, test system.
Targeted to 1/10/2017, Cat Linh Urban Railway – Ha Dong will run inter-system tests (general alignment, no-load test operation, passenger simulator commissioning …) .